Monday, March 5, 2012

Tracking Bangalore-Hassan direct rail line project


I and my friend went for joy ride towards newly laid four lane along NH-48 on 12-Feb-2012. In mid of journey my friend recalled the Bangalore-Hassan rail line construction project that is under progress. The project currently has stopped near Solur which is 18 kms from Nelamangala. From Bangalore to Nelamangala the rail line is already in place.
JALAHALLI CROSS ELEVATED HIGHWAY
4 LANED NELAMANGALA-MANGALORE HIGHWAY

Let me brief on the project. Bangalore to Hassan has multiple rail routes. However all of them are lengthy routes. The first one is via Mysore and the other one via Tumkur. The road way is direct route via Nelamangala and Kunigal. The Bangalore-Hassan direct rail line project is also on the same lines as road to connect Hassan in a shortest path. The rail path from Shravanabelagola to Hassan is completed while from Nelamangala to Shravanabelagola new rail line has to be laid out.
So what is the use? This basically gives faster rail access to Mangalore. The journey from Bangalore to Mangalore will be matter of 7-8 hrs. Current time duration is 12hrs via Mysore and 10-11hrs via Tumkur. Faster access to port city means, faster goods transport. This also saves money for railways as well as vendors who directly or indirectly depend on port facilities. It also saves time for people who are commuting en-route. This also reduces congestion along Tumkur as well as Mysore rail links. The section of rail line is also highly profitable since it connects port city and capital city in faster manner. Also the fares are very minimal in railways.
What is the progress? As per railways standard! Lethargic, as always. The progress is only in terms of earth work and that too some patch work in between. We saw that there was no progress after Solur except awkward dig-up. Some of the works in between like a bridge near Nelamangala is still not complete. Also in most of the places the civil equipments were not seen. Here are some pictures of the project.
ABANDONED WORK NEAR SOLUR
RAIL LINE RUNS PARALLEL TO NH-75 NEAR SOLUR
Only in some areas civil work was progressing. The work is not even properly commenced from Nelamangala. It is really sad that railways is so much lethargic on this new rail line. South-Westrern railway is one of the profit making division under railways and even then railways is giving a step-motherly treatment to this line.
COMPLETED EARTH WORK NEAR SOLUR
ONE MORE VIEW OF COMPLETED WORK
WE RODE ALONG THE RAIL LINE
MINOR BRIDGE
ABANDONED WORK
CIVIL WORK NEAR LAKE PROGRESSING
Why is this? There are basically few main points
1) Bus-Lobby: The major show-stopper is bus lobby. There are hundreds of buses running from Bangalore to coastal areas of Karnataka. If a direct train runs, it will have large impact on their business.
2) Land-acquisition: This can be major hurdle too. However railways do not require much area other than stations. It can be sorted out amicably unless residential areas occur in between.
3) Political-Influence: The people representatives of the entire region also seemed to have no interest on the project. This may be direct influence of (1) stated above. It is also believed that some are owners of buses too which makes it impossible to have their attention.
4) Funding: Railways are not funding properly too. Every year project cost is increasing however the fund allocated is far too less for the project. This is again direct result of (3) which is related to (1)
5) Lack of Interest: People or press also seemed to have interest in these matters. The press which always breaks unnecessary news never bothers to broadcast people friendly reports. If at all the press had an active role, the project would have completed far early.
When will the project be commissioned? As per the current progress, it may take more than 50 years!! People will have to really come forward to accelerate the project. While coming back we were very much annoyed to see the progress. We went along some of the rail paths too. The earth work seems to be good however has seen many rainy days since it was completed (we could see long grasses). Some rail lines are very close to NH-48. This is also bad idea keeping in mind that future the path may be 6-laned [Forget doubling of rail line :-)]
Thanks to smart phone of my friend because of which we could access even corner roads and locations using google maps. That really helps if you have healthy mobile network in the area. The maps guided properly along state highway as well as in village roads along the construction path. We did not take any help from villagers for traversing the path. The google map is pretty much accurate and up to date!

21 comments:

  1. Yes...no press or TV Channel is reporting this. Bangalore-Nelamangala track is ready but no trains...Yesterday i was passing near soladevanahalli...plants are grown on the track and may be it become tree after some time..We have to start pinch the railways by strike. For strike best idea is go to bangarpet and stop trains (let outsiders feel the pinch)...:)

    ReplyDelete
    Replies
    1. Sorry for late reply. I feel MPs are non responsive to such problems. Neither people like us do anything other than writing blog. Strike requires lot people who are really interested for the cause. Thank you for reading and showing concern :-)

      Delete
  2. Good work.
    WE HAVE TO CATCH MUNIYAPPA. HE HAS NOT DONE ANY THING TO KARNATAKA SO FAR EXCEPT SOME TRAIN INAGURATIONS.

    AND EVEN USELESS LEADERS LIKE (MOST OF THE RAILWAY MINISTERS) SIMPLY ADDED LINES IN THEIR OWN STATES INSTEAD OF CONCENTRATING ON ON GOING PROJECTS.

    RAILWAYS IS SO CORRUPT AND DIRECTION LESS DEPARTMENT IN OUR COUNTRY.

    WHAT EVER CRORES OF RUPEES OF PUBLIC MONEY SO FAR SPENT ON SUCH RAILWAY PROJECTS HAS GONE IN TO THE POCKETS OF CONTRACTORS IN TURN TO POLITICIANS.

    RAILWAYS HAS TO BE PRIVATIZED.

    WE HAVE TO GO FOR AN RTI TO CHECK HOW MUCH SPENT ON WHAT WORK FOR THESE MANY YEARS,WHEN 40 TO 50 KMS OF METRO WORK IS GETTING COMPLETED IN BUSY BANGALORE / DELHI WITHIN 10 YEARS,BUT LESSER COSTING RAILWAY LINES ARE NOT GETTING FINISHED EVEN AFTER 15YEARS (FROM DEVEGOWDA'S PERIOD) MEANS.

    WE ARE NOT QUESTIONING THE PEOPLE.

    WE CAN NOT BLAME BUS CONTRACTORS,THAT IS THEIR LIFE THEY HAVE TO SURVIVE.
    ONLY RAILWAYS IS RESPONSIBLE FOR THE DELAY.LIKE THEIR TRAIN SCHEDULES, EVERY THING IS RUNNING LATE.

    ReplyDelete
    Replies
    1. Thank you for your time reading the blog Mr.Srinivasa and apologize for late reply.

      Politicians except those from Karnataka have always been biased to their states. I believe Railways can be semi privatized without affecting poorer section of society. Trains running late is of-course due to poor infrastructure. I have even heard that there has been under-table activities between railways and bus owners to mitigate the construction work (Most of the bus owners are politicians in coastal karnataka at-least).

      Once again Thank you and have great time!

      Delete
  3. This comment has been removed by a blog administrator.

    ReplyDelete
    Replies
    1. Please do not spamify the post. Please read only if you are really interested

      Delete
  4. Replies
    1. Thank you for reading blog. I hope at least some part of work of rail work will materialize soon.

      Delete
  5. Informative post. Probably one way out is to file RTIs to the Divisional Railways and ask for information. ask multiple people to file RTIs and force information out of the officers.
    What lacks in India is Transparency. There is a cloud of mystery on all things and this helps officials and politicians get away.
    It is surprising that people esp. educated people, do not come out in support of such projects, nothing will happen if we just sit and crib about it.

    ReplyDelete
    Replies
    1. Thank you for comment. Yes nothing is going to happen by just writing blog. It can only awaken people. Then it is up to the people to take forward including myself.

      Delete
  6. its a very good post Mr.Nanda kumar..I am from kunigal and i daily travel to bangalore by bus..Monthly pass is too costly and also coming in the bus ,piercing the traffics of gorguntepalya and jalahali cross is like crossing the hell..Like me many from kunigal are travelling in bus daily to blre..It will be very helpful to all of us if tracks are laid down soon...

    ReplyDelete
    Replies
    1. Thank you for reading. There are lot of people like you who are facing problems. The pace with which the project is progressing is really total embarrassment. I have not checked the current status thought however it was 41kms behind kunigal. Even I guess the current status may have progressed further by few meters

      Delete
  7. Thanks,It's a good posting. I am a resident of Nelamangala and daily traveling to Bangalore city for work. It will be good if they start Bangalore-nelamangala train (already sanctioned in 2010-11 budget)also. I am also waiting for this new route (Bangalore-Hassan via nelamangala).
    Because of these corrupted politicians this work is going very slowly.
    This is same everywhere in India.

    Our bad luck to have such culprit politicians still.

    God only has to save us.

    ReplyDelete
    Replies
    1. Thank you for reading. Many people from Bangalore to Mangalore are eagerly waiting for the line to commission. Slowness has many reasons major being the inherent biased treatment of railways

      Delete
  8. Hi Nanda Kumar, Its been a year since you posted this blog. Any updates on the progress hopefully???

    ReplyDelete
    Replies
    1. Few days back I did travel to mangalore during day time. Along highway near Kunigal and Hirisaave I saw considerable earth and bridge works progressing. I see now work past solur now. However, did not get chance to exclusively visit for that purpose.

      Delete
  9. Nice to read your article. I too share the same concern with you. It is we the people from the coast that are very lethargic, complacent and ignorant. We are OK with whatever we have and ADJUST with the available infrastructure. The leaders/ politicians/ MP's/ MLA's are all concerned with their own business - construction/ travels etc. It is for their vested interests they are keeping the overall development of the coastal region at bay.

    ReplyDelete
    Replies
    1. Thank you for reading! Yes due to lethargic nature of us, the maximum advantage of Konkan Railway is being taken by other people :(. The apathy of Shiraadi Ghat Road is one more such example. We have to fight for new Mangalore Division as well which has been only dream as of now

      Delete
  10. any update of work on this line?

    ReplyDelete
    Replies
    1. Did not find time to visit. However the work has progressed past solur and I have seen considerable earth work being carried out near Kunigal and Hirisaave (Atleast from NH view).